- This method provides system operators with a lightweight, small and easy to apply technology. All parts of the DAC HV200 test equipment can easily be covered with flight cases and fit into a van/truck with a cargo load below 1.000kg. The application takes approx 5 to 6 hours:
+ DAC HV200 system assembly on site (1 hour)
+ Connection of all parts and checking of system (0,5 hours)
+ Testing and measurement of all three phases of a system (3 hours)
+ Analysis of the measuring results - disconnection and packing of test system into transportation boxes (1 hour)
- Low energy consumption on site – small footprint for test equipment
- Only two engineers are needed to execute the full test
- Cable system shut-down time will be minimized to 4 to 5 hours
- Voltage withstand test automatically monitored by partial discharges
- Results of non-destructive and sensitive PD measurement and tan δ are available on the same day
- This approved testing methodology is in accordance with relevant international standards and recommendations (IEEE, IEC, CIGRE)